Cairo International Airport
Airfield ground lighting
Project description
- Construction of the third runway of 4,000 m long and 65 m wide
Customer challenges
- Replace the current cross runway, increasing the capacity of the airport to 120 movements per hour
Nexans solutions
- 500 km of 5 kV primary cable that will provide power to the lighting transformers, and 80 km of H07RN-F secondary cable
- Cables comply with all international specifications for airfield applications